PrepAway - Latest Free Exam Questions & Answers

Which of the following will be affected?

Additional company employees have been assigned to the project. Which of the following
will be affected?

PrepAway - Latest Free Exam Questions & Answers

A.
Total project cost will be reduced because the project can now be completed sooner.

B.
The quality of the product will improve but it will add more time to the project to train the
new employees.

C.
The timeline may be positively affected at the expense of the project cost.

D.
This change does not affect the triple constraint because the additional employees are
already on the company payroll.


Leave a Reply