Which of the following actions would be BEST for the project manager to take?

The project manager has been informed the project’s CPI is 0.85 on a multi-year project that
is 30% complete. Which of the following actions would be BEST for the project manager to
take?

PrepAway - Latest Free Exam Questions & Answers

A.
Ask the project sponsor to extend the project schedule.

B.
Submit an RFQ to find a less expensive material.

C.
Assign additional team members to Quality Control.

D.
Fast track the project to reduce risk.