Which of the following is the project manager building?

A project manager is entering the list of a project’s activities with their estimated begin and
end time to visualize which activities overlap and when the project is scheduled to end.
Which of the following is the project manager building?

PrepAway - Latest Free Exam Questions & Answers

A.
Gantt chart

B.
Work Breakdown Structure

C.
Critical Path

D.
PERT chart