which of the following components of the project plan should this be documented?

A project has just finished performance testing and found that the application can only
handle 100 concurrent users where the requirement was to handle 500 concurrent users. In
which of the following components of the project plan should this be documented?

A. Change form

B.
Scope statement

C.
Issues log

D.
WBS