PrepAway - Latest Free Exam Questions & Answers

Which of the following should be performed by the project manager?

The project team is geographically split between two time zones. Which of the following
should be performed by the project manager?

PrepAway - Latest Free Exam Questions & Answers

A.
Convert traditional meetings into email updates and catch up on an exceptions basis.

B.
Schedule two separate meetings at the desired local time for the participants.

C.
Escalate to the project sponsor with a preference to replace the remote members with
local members.

D.
Set up meeting times that are not necessarily a perfect fit, but are fair to both locations.


Leave a Reply