PrepAway - Latest Free Exam Questions & Answers

which of the following risk response strategies?

The customer has agreed to pay 20% more for the project deliverable if it can be turned
over to them in four weeks. The project manager has the team members to complete the
project, but is having difficulty procuring enough material from a vendor. The project
manager agrees to pay 5% more for the material if complete shipment can be made within a
week. This is an example of which of the following risk response strategies?

PrepAway - Latest Free Exam Questions & Answers

A.
Transferring

B.
Enhancing

C.
Sharing

D.
Exploiting


Leave a Reply