Which of the following processes allowed the project manager to make this determination?

In QC testing, the project manager determines that the deliverable is outside of the
specification limits. Which of the following processes allowed the project manager to make
this determination?

PrepAway - Latest Free Exam Questions & Answers

A.
Identify variance

B.
Review change log

C.
Regression analysis

D.
Monitoring work performance