which of the following methods is being used if risk identification is difficult and time-consuming?

When evaluating project management risks, which of the following methods is being used if
risk identification is difficult and time-consuming?

PrepAway - Latest Free Exam Questions & Answers

A.
Quantitative analysis

B.
Narrative analysis

C.
Qualitative analysis

D.
Probability analysis