A change request has been approved for a project. Which of the following actions should be
taken FIRST by the project manager?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform an analysis to determine the impact on the project

B.
Create an updated Pareto chart

C.
Update the appropriate project plan documents

D.
Identify project cost and schedule variances