Which of the following is the BEST method to avoid staffing conflict between resource managers and project man

Which of the following is the BEST method to avoid staffing conflict between resource
managers and project managers?

PrepAway - Latest Free Exam Questions & Answers

A.
Ask the project sponsor for team member assignments.

B.
Claim the best department resources before the project starts.

C.
Formally request team members early.

D.
Allow team members to enter the project as best fits their schedule.