The project manager MUST:

After a project team has almost completed the development on the project’s original
requirements, the users identify functionality that is necessary but was not in the original
requirements. The project manager MUST:

PrepAway - Latest Free Exam Questions & Answers

A.
Generate a change request.

B.
Update the risk register.

C.
Implement the change.

D.
Cancel the project.