PrepAway - Latest Free Exam Questions & Answers

Which of the following methods should the project manager consider?

An approved change request has delayed the project start date without modifying the
completion date. The project sponsor has requested the project manager to pursue an
option with the LOWEST initial cost. Which of the following methods should the project
manager consider?

PrepAway - Latest Free Exam Questions & Answers

A.
Parametric estimating

B.
Rolling wave planning

C.
Crashing

D.
Fast tracking