Which of the following should the project manager do NEXT?

While in an operations meeting, the project manager hears that a new enhancement is
being released that will impact the agreed upon scope. Which of the following should the
project manager do NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
Identify the issue, perform an analysis, and create a change request

B.
Log the change and communicate it to the project team

C.
Inform the sponsor while allowing the change to continue

D.
Stop the development, communicating that changes have to be approved

Explanation: