A project manager has been asked by a major stakeholder to modify the scope of a project
in progress. Which of the following is the best FIRST step?

PrepAway - Latest Free Exam Questions & Answers

A.
Assess the impact the change will have on the project.

B.
Call a meeting and ensure all stakeholders agree to the changes.

C.
Submit a change request to the PMO.

D.
Obtain written approval from the project sponsor and make the requested changes.

Explanation: