The project manager is reviewing the earned value of work completed compared to the
planned value and is representing it in a dollar figure. This type of analysis is an example of
which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost performance index

B.
Risk mitigation

C.
Schedule variance

D.
Cost variance