which of the following actions should the project manager do NEXT?

After a change control board meeting, which of the following actions should the project
manager do NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
Notify the requester of the verdict.

B.
Review the impact of proposed change.

C.
Update the project scope statement.

D.
Document the specific change request.