A project manager has a project with staff in four different countries. When generating the
resource management plan, which of the following should be considered FIRST?

PrepAway - Latest Free Exam Questions & Answers

A.
Understanding the international country code of all the team members.

B.
Locating each employee on the map in the office.

C.
Getting the email address of all the employees.

D.
Reviewing holiday and vacation schedule with all team members.

Explanation: