Which of the following actions should the project manager take NEXT?

The project manager has received an approved change request. Which of the following
actions should the project manager take NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
Develop a plan to incorporate the change into the project

B.
Schedule a meeting with the change advisory board to discuss the impact of the change

C.
Perform a probability and impact assessment on the approved change

D.
Hold a team meeting to ensure the change is immediately implemented