PrepAway - Latest Free Exam Questions & Answers

Which of the following is TRUE regarding this project?

A project with a projected budget of $100,000 is 75% complete and has a CPI of .85. Which
of the following is TRUE regarding this project?

PrepAway - Latest Free Exam Questions & Answers

A.
More project work than projected has been completed

B.
The project is currently in cost overrun

C.
The project EV is 63.75

D.
$85,000 has been spent in the project

Explanation: