PrepAway - Latest Free Exam Questions & Answers

Which of the following should the project manager do?

The key stakeholder requires the project manager to advance the completion date before
funding runs out. The project manager has had problems with this stakeholder in the past
and wants to document this request. Which of the following should the project manager do?
(Select TWO).

PrepAway - Latest Free Exam Questions & Answers

A.
Complete a project change request form.

B. Analyze the project impact.

C.
Update the project scope statement.

D.
Revise the scope management plan.

E.
Monitor the work performance.

2 Comments on “Which of the following should the project manager do?


Leave a Reply