Which of the following should the project manager do to ensure stakeholder expectations are met?

Ann, one of the affected stakeholders, feels that the project team has not been giving
periodic stakeholder updates and that her input has not been taken into account. Which of
the following should the project manager do to ensure stakeholder expectations are met?

PrepAway - Latest Free Exam Questions & Answers

A.
Ensure that Ann is involved during the testing phase of the project so she can call out
functional gaps

B.
Organize a walkthrough of the solution and ensure face-to-face updates occur every two

weeks

C.
Escalate the issue to the project steering committee that Ann is criticizing the project
quality

D.
Organize a requirements workshop to capture any gaps