PrepAway - Latest Free Exam Questions & Answers

The project manager determines the impact to be low; therefore, the MOST likely response to the identified ris

There is a high probability of a needed resource becoming unavailable. The project
manager determines the impact to be low; therefore, the MOST likely response to the
identified risk is to:

PrepAway - Latest Free Exam Questions & Answers

A.
Accept it

B.
Mitigate it

C.
Avoid it

D.
Minimize it


Leave a Reply