Which of the following statements highlights key performance indicators to be documented in the project scope?

Which of the following statements highlights key performance indicators to be documented
in the project scope?

PrepAway - Latest Free Exam Questions & Answers

A.
IT staff will be able to maintain the project after completion

B.
Efficiency gains will enable five fewer days to provide staff access

C.
There will be a reduction in technology costs of one million dollars a year

D.
The solution will not include integration with the finance system