Which of the following documents would clarify the discrepancy?

During customer acceptance, a project manager meets with the stakeholders who claim a
bridge was built with two toll gates instead of three. Which of the following documents would
clarify the discrepancy?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk Management Plan

B.
Closeout report

C.
Scope Statement

D.
Lessons Learned