Which of the following network diagram methods would be MOST appropriate?

The project team determined that using a multipoint estimate is more appropriate than
single point estimate. Which of the following network diagram methods would be MOST
appropriate?

PrepAway - Latest Free Exam Questions & Answers

A.
Critical path

B.
PERT

C.
GERT

D.
Critical chain