This type of modeling relies on:

A project manager is trying to ensure the quality of the design and reduce the number of
potential defects. The project manager would like to use the fishbone diagram to perform
this analysis. This type of modeling relies on:

PrepAway - Latest Free Exam Questions & Answers

A.
Determining the number of events.

B.
Prioritizing the specific event.

C.
Variance in the process over time.

D.
Causes of a specific event.