PrepAway - Latest Free Exam Questions & Answers

which of the following actions should be taken?

A key supplier has informed the project manager that there will be a two month delay to
fulfill an order. Which component of the project plan is affected and which of the following

actions should be taken?

PrepAway - Latest Free Exam Questions & Answers

A.
Manage scope and consider a project change request.

B.
Evaluate the project schedule and raise a project issue.

C.
Manage project quality and schedule a meeting.

D.
Implement approved changes by utilizing a change management form.


Leave a Reply