Which of the following should be done to ensure the change is implemented within the prescribed timeframe?

As part of the planning process, the change control board meets every other week.
Immediately after the last change control meeting, a primary examiner called and indicated
a new regulation was passed and must be implemented within ten days. Which of the
following should be done to ensure the change is implemented within the prescribed
timeframe?

PrepAway - Latest Free Exam Questions & Answers

A.
Ask the regulator for an extension of time

B.
Wait for the next change control meeting and introduce it then

C.
Incorporate it as a task into the project plan and begin making the change

D.
Review the change control procedures for emergency changes

Explanation: