PrepAway - Latest Free Exam Questions & Answers

Which of the following actions should the project manager do FIRST?

A company is replacing their file server with a new one. During the data migration, the old
file server experiences critical hardware failure. The data migration cannot continue until the
hardware is replaced. This repair will put the project behind schedule by a week. Which of
the following actions should the project manager do FIRST?

PrepAway - Latest Free Exam Questions & Answers

A.
Prepare performance report

B.
Manage the issue

C.
Schedule a meeting

D.
Update communication plan


Leave a Reply