PrepAway - Latest Free Exam Questions & Answers

Which of the following is the BEST option to meet the deadline?

A project is in the execution phase. In review, Joe sees that the project will miss the next
deadline due to delays in equipment delivery. Joe has asked the resource manager for
additional resources, has been denied, and reminded that the deadline cannot be missed.
Which of the following is the BEST option to meet the deadline?

PrepAway - Latest Free Exam Questions & Answers

A.
Crash the schedule

B.
Log the risk in the risk register

C.
He should perform the work needed

D.
Report to the project sponsor that the deadline will be missed

Explanation:

4 Comments on “Which of the following is the BEST option to meet the deadline?

  1. Pollo says:

    I dont agree with the availible options. Crashing requires that additional resources are used to speed up the process. I would chose to run task parallel. However not an option




    0



    0
  2. Todd The Bod says:

    No way it is crashing as it states in the question that Joe’s request for additional resources was denied- which would be crashing.

    It looks like his only option would be to tell the project sponsor as he has the authority to seek out remedy for the situation.

    Logging it as a risk doesn’t make sense because he already knows it is an eventuality- “Joe sees that the project WILL miss the next deadline”

    Performing the work doesn’t wouldn’t remedy the situation as the delivery of the equipment is out of his hands.

    I believe the answer would be D.




    0



    0

Leave a Reply