A project stakeholder wants to make changes to a project after work on the project has
already started. Which of the following should the project manager do FIRST?
A.
Submit stakeholder’s change request to the change control board
B.
Perform an analysis on the requested change submitted by the stakeholder
C.
Assign the request a tracking number and record in change request log
D.
Recruit new project team members to expedite the change’s completion date
A or B would most likely be the best couple of answers here. Some documentation says to perform the analysis after your submit the change request to the board- some suggests your do this before.