PrepAway - Latest Free Exam Questions & Answers

Which of the following should the project manager do FIRST?

A project stakeholder wants to make changes to a project after work on the project has
already started. Which of the following should the project manager do FIRST?

PrepAway - Latest Free Exam Questions & Answers

A.
Submit stakeholder’s change request to the change control board

B.
Perform an analysis on the requested change submitted by the stakeholder

C.
Assign the request a tracking number and record in change request log

D.
Recruit new project team members to expedite the change’s completion date

2 Comments on “Which of the following should the project manager do FIRST?

  1. Todd The Bod says:

    A or B would most likely be the best couple of answers here. Some documentation says to perform the analysis after your submit the change request to the board- some suggests your do this before.




    0



    0

Leave a Reply