Which of the following does the project manager need to update?

The customer now needs the project’s deliverable 3 months earlier than scheduled. The
deliverable’s quality has been reduced so the budget will not be impacted. Which of the
following does the project manager need to update?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule

B.
Project budget

C.
Issues Log

D.
Communications Plan