PrepAway - Latest Free Exam Questions & Answers

which of the following is correct?

The project has spent $5,000 to date. The earned value of the project is $7,500. Using
earned value management, which of the following is correct?

PrepAway - Latest Free Exam Questions & Answers

A.
The project is under budget.

B.
The project is ahead of schedule.

C.
The project is over budget

D.
The project is behind schedule.

3 Comments on “which of the following is correct?

  1. Todd The Bod says:

    The project may not have yet exceeded the budget. However, there isn’t enough information to know if it is under budget at the current percent of completion.

    Kind of an unfair question.




    0



    0

Leave a Reply