Which of the following approaches would be BEST to determine the cost?

A new team has been put together for a construction project. The project currently does not
have a cost estimate but the company has done other builds similar to the one at task and
needs the estimate at the end of the week. Which of the following approaches would be
BEST to determine the cost?

PrepAway - Latest Free Exam Questions & Answers

A.
Expert judgment

B.
Analogous

C.
Bottom up

D.
Top down

Explanation: