which of the following should occur NEXT?

A change request has been identified and submitted to the Change Control Board for
approval. After gaining approval, which of the following should occur NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
Document using the appropriate change control forms

B.
Perform impact analysis

C.
Update the project plan components

D.
Request a meeting with the project sponsor

Explanation: