Which of the following should be done NEXT?

A project team member has identified a required change to one of their assigned tasks. The
change would alter the order in which other tasks must be completed. Which of the following
should be done NEXT?

PrepAway - Latest Free Exam Questions & Answers

A.
Perform an impact analysis

B. Implement the change

C.
Update the change registry

D.
Document the change