A WBS dictionary:

A WBS dictionary:

PrepAway - Latest Free Exam Questions & Answers

A.
allocates the WBS components to appropriate teams or named individuals within teams.

B.
describes how a project will be decomposed into smaller, manageable subprojects or
work packages.

C.
provides a description of all of the components of a WBS, and a brief summary of its
SOW, scope and deliverables.

D.
is a granular hierarchical breakdown of the work to be undertaken by the project team, to
meet the objectives of the project.

Explanation: