Which of the following is a KEY requirement to produce a project schedule?

Which of the following is a KEY requirement to produce a project schedule?

PrepAway - Latest Free Exam Questions & Answers

A.
Ensure all the resourcing costs are known

B.
Identification of all the required activities

C.
The program evaluation and review technique

D.
A stakeholder and customer matrix