Which of the following is the project manager implementing when they allocate…?

Which of the following is the project manager implementing when they allocate additional

resources to a set of tasks that are in the critical path and are slowing down the project
completion?

PrepAway - Latest Free Exam Questions & Answers

A.
Crashing

B.
Optimizing

C.
Controlling

D.
Fast tracking