Which of the following shows how often contracts would be closed for the procurements on a project?

Which of the following shows how often contracts would be closed for the procurements on
a project?

PrepAway - Latest Free Exam Questions & Answers

A.
At the end of the contract

B.
During phase gate review

C.
After the project is completed

D.
At the end of the project