PrepAway - Latest Free Exam Questions & Answers

Which of the following is MOST likely to occur?

After the ground breaking at a new construction site, the pile driving operation comes to a
full stop due to the nature of the terrain. Which of the following is MOST likely to occur?

PrepAway - Latest Free Exam Questions & Answers

A.
The project communication plan must be updated and a stakeholder meeting must be
scheduled.

B.
The project manager must manage the new issue as the project schedule could be
delayed.

C.
The project manager must implement conflict resolution and review the resource
requirement.

D.
The project scope statement must be reviewed and the project manager must prepare a
performance report.


Leave a Reply