An organization has started a project to upgrade all computers in an organization. During
the implementation phase of the project, the computer vendor notifies the project manager
that the computer systems are on backorder. The vendor anticipates delivery of the systems
within five business days. Which of the following resource leveling techniques would be
MOST appropriate in this scenario?

A.
Optimizing
B.
Delaying
C.
Fast tracking
D.
Crashing