During project execution, the cost management plan would be used to:
A.
Determine if variances exceed a defined threshold.
B.
Identify costs that were not previously identified.
C.
Schedule resources for each phase of the project.
D.
Ensure that resources are compensated fairly.
A.
Determine if variances exceed a defined threshold.