Which of the following activities are associated with the closing phase of a project? (Choose two.)

Which of the following activities are associated with the closing phase of a project? (Choose two.)

A. Risk mitigation

B. Arc

hiving of project documents

C. Tracking of expenditures

D. Lessons learned

E. Quality assurance

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 338, 339