PrepAway - Latest Free Exam Questions & Answers

A new project sponsor has joined the project team, and the constraints on the project have been reprioritized.

A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but t

he new sponsor has indicated that meeting a new, shorter deadline is the priority.

Which of the following effects is this MOST likely to have on the project?

A. The deliverables and quality will remain the same, but the cost will increase.

B. The deliver

ables and quality will remain the same, but the cost will decrease.

C. The deliverables and cost will remain the same, but the quality will increase.

D. The cost and quality will remain the same, but the deliverables will increase.

QUESTION


Leave a Reply