A project requires daily status updates.

A project requires daily status updates.

Which of the following is the MOST effective method for providing these updates?

A. Backlog

B. Standup

C. Kickoff

D. Retrospective

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306