A project team is overseeing the installation of a new rep

tile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.

Which of the followi

ng constraints are MOST likely to be affected? (Choose two.)

A. Quality because the existing system is now outside the threshold.

B. Requirements because this is a change to initial scope.

C. Cost because replacing the system incurs additional expense.

D.

Schedule because this was an unscheduled task and will impact the timeline.

E. Stakeholders because they will need to understand the modification and provide buy-in.

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,

Indianapolis, 2017, p. 293