There are four parallel paths on a network diagram. The summary duration of each path is below

:

A, C, G: 10 weeks

A, B, F: 8 weeks

D, E, H: 12 weeks

D, B, F: 7 weeks

Which of the following tasks are on the critical path?

A. A, C, G

B. A, B, F

C. D, E, H

D. D, B, F

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition,