PrepAway - Latest Free Exam Questions & Answers

A WBS is being developed for a project.

A WBS is being developed for a project.

Which of the following would be BEST suited to contribute cost and time estimates for

the project activities?

A. Project team members

B. Project sponsor

C. Project manager

D. Project scheduler

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82