A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for
the project activities?
A. Project team members
B. Project sponsor
C. Project manager
D. Project scheduler
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82