A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, a

A company

has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.

Which of the following terms describe this requirement?

A. Outsourcing

B. Business

acquisition

C. Business process change

D. Internal reorganization

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297